The report records net irrigated area rising from 4,13,833 hectares in 2015–16 to 4,38,278 hectares in 2024–25, with source-specific changes reported separately.
The report records commissioning in July 2020 and 12,684 hectares irrigated at commissioning. Cumulative expenditure of Rs 1,153 crore covers the long-running project, whose construction began in 1974.
Canal construction and effective water delivery are different; parts of Banasura Sagar and Idamalayar remained incomplete in the report.